High Court decision in Mount Pleasant Coal Mine
1 November 2026 in Business Law | 4 min readThis article examines the High Court’s landmark decision of October 7th 2026 in MACH Energy Australia Pty Ltd v Denman Aberdeen Muswellbrook Scone Healthy Environment Group Inc [2026] HCA 35. The case called into question the scope of planning commissions’ and consent authorities’ powers when approving developments that contribute to greenhouse gas emissions.
Overview
This case concerns the development consent approval that MACH Energy Australia Pty Ltd (MACH Energy) sought from the Independent Planning Commission (Commission).
The Commission approved MACH Energy’s proposal to extend the operational life of the Mount Pleasant open-cut coal mine by 22 years, permitting the extraction of an additional 406 million tonnes of coal and increase annual production from 10.5 million tonnes to 21 million tonnes.
Denman Aberdeen Muswellbrook Scone Healthy Environment Group Inc (DAMSHEG), an Upper Hunter community action group and environmental organisation, challenged the Commission’s approval, arguing in part that the Commission failed to consider:
- the environmental impacts of climate change in the locality of the mine;
- the development’s environmental impacts required by section 4.15(1)(b) of the Environmental Planning and Assessment Act 1979 NSW; and
- conditions aimed at minimising all greenhouse gas emissions, including “Scope 3 emissions”, to the greatest extent practicable under clause 2.20(1)(c) of the State Environmental Planning Policy Resources and Energy 2021 .
“Scope 3 emissions” are indirect greenhouse-gas emissions occurring in an entity’s value chain from sources it does not own or control. In the context of a coal mine, this is principally associated with the downstream emissions produced after export when customers transport and burn coal in overseas jurisdictions.
The First-Instance Proceedings
In the initial Land and Environment Court proceedings, Robson J affirmed MACH Energy’s development consent and dismissed all DAMSHEG’s grounds for judicial review. His Honour was of the view that the Commission had not failed to consider mandatory considerations, by virtue of the approval alone.
The Court preferred MACH Energy’s submissions and corresponding evidence which, broadly summarised, contended that the Commission did consider the development’s Scope 3 emissions, notwithstanding their ultimate conclusion that the relevant impacts would be adequately regulated and accounted for by the relevant jurisdictions and international law.
The Honourable Robson J reasoned that requiring the Commission to address each climate manifestation risked converting judicial review into an impermissible merits review.
The First Appeal
DAMSHEG appealed the Land and Environment Court’s first-instance dismissal, pursuant to section 58(1) of the Land and Environment Court Act 1979 (NSW).
The Panel concluded that the primary judge erred in determining that the Commission did not, as required, consider the impact of climate change on the locality. The judgement construed that section 4.15(1)(b) of the Environmental Planning and Assessment Act 1979 (NSW) (EPA Act):
“…requires the consideration of the causal relationship between the Project and its effects on the locality.”
Thus, one of the two arguments advanced by DAMSHEG succeeded unanimously before Ward J, Adamson JA and Price AJA, and the Commission’s approval for the coal mine was set aside for failure to consider a mandatory consideration.
The Second Appeal
MACH Energy subsequently appealed to the High Court to reverse the NSW Court of Appeal’s decision to set aside the development approval.
Unanimous Findings
Interestingly, all five Justices unanimously ruled that the NSW Court of Appeal had incorrectly construed section 4.15(1)(b) of the EPA Act. The High Court determined that the language of the provision as properly construed, did not compel the Commission to consider the social and economic effects on the locality as a separate consideration, but as part of the global consideration in terms of scope.
Since the Commission considered the Scope 3 emissions in their determination but ultimately decided that these impacts were accounted for, it was held that the Commission had sufficiently discharged its obligation under this provision in their assessment of their contribution to global climate change.
Majority Findings
However, there was a majority ruling on DAMSHEG’s ‘notice of contention’ concerning Scope 3 minimisation conditions.
The majority held that the Commission failed to consider whether the development consent should be subject to conditions aimed at the minimisation of Scope 3 emissions to the greatest extent possible.
Gordon J, Edelman J and Beech-Jones J reasoned that the Commission’s jurisdictional error was the failure to consider whether conditions should be imposed on MACH Energy’s proposal, in light of the large amount of projected Scope 3 emissions, and the character of their discussions surrounding the Scope 3 emissions.
The majority found, on the evidence, that the Commission’s discussions of the projected Scope 3 emissions focused on where those emissions would be counted or regulated, rather than any minimisation strategy. This ultimately resulted in a finding that the Commission did not discharge its obligation under clause 2.20 of the State Environmental Planning Policy Resources and Energy 2021 NSW.
Their Honours also found the error material because there was a real possibility that consideration of Scope 3 conditions could have affected the decision or the conditions attached to the development consent.
Dissenting
Gageler CJ and Jagot J dissented on the issue of clause 2.20 of the State Environmental Planning Policy Resources and Energy 2021 NSW. Their honours considered that the Commission’s reasons for the lack of conditions imposed, adequately demonstrated appropriate consideration.
This view and legal reasoning were broadly consistent with Robson J’s original determination.
Commentary
The landmark decision established a much higher threshold for consent authorities when assessing mining, petroleum and extractive industry projects.
The public authorities must make a genuine and express consideration on whether the imposition of conditions could minimise green house gas emissions, including indirect Scope 3 emissions, to the greatest extent practicable.
An approval that is absent of this consideration, may constitute jurisdictional error and invalidate the approval.
State Government Response
Recent media reports indicate that the NSW Government immediately commenced considering legislation to avoid the impact of this decision.